旋挖钻机与冲击钻机组合施工灌注桩的工程实践

In foundation engineering, complex geological conditions often require the combined use of different construction equipment to improve efficiency, stability, and overall pile quality. The Nanchong Junhui Shangpin project adopted a combined method of rotary drilling rigs and impact drilling rigs to solve problems such as borehole collapse, loose backfill, and mixed strata conditions. This approach significantly improved construction efficiency, reduced rework, and delivered strong economic benefits.

1. Project Overview

The Nanchong Junhui Shangpin project is a large residential development with a total construction area of about 600,000 m² and a 33-story main building. The pile foundation works for phases 4–8 involve complex geological conditions. The upper 15 meters consist of backfill soil, while the lower 15–30 meters consist of strongly to weakly weathered mudstone. The design requires piles to penetrate at least 3 meters into the weakly weathered mudstone, using rotary bored piles with grouting technology.

2. Construction Challenges

During rotary drilling, several issues were encountered. In silty soil layers, boreholes were prone to shrinkage and collapse. Riverbed deposits containing quicksand caused instability and repeated collapse. Thick backfill layers with large stones created voids, leading to grout leakage and hole failure. These problems increased construction difficulty, caused delays, and raised costs due to repeated drilling and backfilling.

3. Combined Construction Method

To address these issues, a combined construction method was adopted.

Impact drilling rigs were used in the upper unstable layers to compact loose soil, break large stones, and stabilize silty and quicksand formations. This helped prevent borehole collapse and improved ground stability.

Rotary drilling rigs were then used in the lower stable rock layers, particularly in strongly and weakly weathered mudstone, to achieve efficient and precise drilling.

The process involves using impact drilling first to stabilize the upper strata, followed by rotary drilling to complete the lower rock drilling and final pile formation. This combination ensures both stability and efficiency.

4. Key Construction Technical Points

Before construction, the site must be leveled and properly planned. Steel plates should be used under equipment to improve ground bearing capacity and prevent sinking or displacement. Casings should be pre-installed to support subsequent operations and avoid delays.

During construction, loose soil layers should be backfilled with loess and compacted repeatedly. In quicksand areas, boulders should be added for compaction to improve stability and prevent collapse during rotary drilling. In areas with large stones, preliminary excavation and backfilling should be carried out to ensure smooth casing installation.

Drilling diameter and verticality of the impact rig must be strictly controlled to ensure proper transition to rotary drilling without borehole damage. For stabilized boreholes, sufficient compaction must be achieved before handing over to the rotary drilling rig.

Mud management is also critical. Clay mud is used for impact drilling to improve compaction, while high-quality bentonite slurry is used for rotary drilling to maintain borehole stability and prevent collapse.

5. Construction and Site Management

Personnel coordination is essential. Clear division of responsibilities among construction teams helps avoid delays and ensures smooth workflow. Construction sequencing must be carefully planned according to site conditions and schedule requirements. Effective communication between technical staff and operators helps improve efficiency and execution quality.

Material and equipment management must also be optimized. Equipment should be arranged to avoid interference between different operations. Limited site space requires rational stacking of materials and efficient use of available resources. Reuse of materials should be encouraged to reduce waste and control costs.

6. Safety Control Measures

Equipment safety requires proper foundation leveling and compaction before rig installation. The drilling rig must be correctly aligned to prevent tilting or shifting during operation. Trial lifting should be conducted before final positioning.

Electrical safety must be strictly managed. All cables should be properly insulated and protected. Grounding systems for welding and distribution equipment must be checked regularly. Leakage protection devices should be inspected frequently, and maintenance must be carried out with power disconnected and warning signs in place.

7. Conclusion

Impact drilling rigs are effective in compacting and breaking large, hard materials, but they are relatively slow and costly. Rotary drilling rigs offer high efficiency and speed but have limitations in unstable or soft strata. By combining both methods, their advantages can be fully utilized.

In practical engineering, the reasonable integration of rotary drilling rigs and impact drilling rigs improves construction efficiency, enhances pile quality, and reduces overall cost. This combined construction method is especially suitable for complex geological conditions and provides a reliable solution for modern foundation engineering projects.